Student Publications
Author: Senthil Seliyan Elango
Title:
Railway Engineering
Area:
Country :
Profile:
Program:
Available for Download:
Yes
Sharing knowledge is a vital component in
the growth and advancement of our society
in a sustainable and responsible way. Through
Open Access, AIU and other leading institutions
through out the world are tearing down the
barriers to access and use research literature.
Our
organization is interested in the dissemination
of advances in scientific research fundamental
to the proper operation of a modern society,
in terms of community awareness, empowerment,
health and wellness, sustainable development,
economic advancement, and optimal functioning
of health, education and other vital services.
AIU’s mission
and vision is consistent with
the vision expressed in the Budapest Open
Access Initiative and Berlin Declaration
on Open Access to Knowledge in the Sciences
and Humanities. Do you have something you
would like to share, or just a question
or comment? We would be happy to hear from
you, please use the Request Info link below.
For more information on the AIU's Open Access
Initiative, click
here.
|
|
|
|
|
|
INTRODUCTION
Rail transport is
the transport of
passengers and
goods by means of wheeled vehicles
specially designed to run along railways or railroads. Rail
transport is part of
the logistics
chain, which facilitates the
international
trading and
economic growth in most countries.
A typical railway/railroad
track consists of two parallel
rails, normally made
of steel,
secured to cross-beams,
termed
sleepers (U.K.)
or 'ties' (U.S.). The sleepers maintain a
constant distance between the two rails; a measurement known as
the 'gauge' of the track.
To maintain the alignment of the track, it is either laid on a bed
of ballast or else secured
to a solid concrete
foundation, and the whole is referred
to as Permanent way.
Railway rolling stock, which is fitted with metal wheels, moves with
low frictional
resistance when compared to road vehicles; on the other hand
locomotives and power
cars normally rely solely for traction on the point of contact of
the wheel with the rail
whence they obtain adhesion i.e. the part of the transmitted axle
load that makes the
wheel "adhere" to the smooth rail. Whilst this is usually sufficient
under normal dry rail
conditions, adhesion can be reduced or even lost through the
presence of unwanted
material on the rail surface, such as grease, ice or dead leaves
DESCRIPTION
Permanent way is the generic term for the track � rails,
sleepers and ballast � on which
railway trains run. British practice has diverged quite sharply from
that in North America
and continental Europe. Although the configuration of the track
today would be
recognized by engineers of the 19th century, it has developed
significantly over the years
as technological improvements became available, and as the demands
of train operation
increased.
However the traditional form consists of
two parallel iron or steel rails, a fixed distance apart, on which
the wheels of
trains run,
transverse beams called sleepers, set at a close spacing, that
maintain the specified
spacing of the rails and that distribute the concentrated loading of
train wheels,
fastenings to hold the rails and sleepers together,
a layer of mineral ballast placed under and around the sleepers, to
further
distribute the train loading, and to resist lateral displacement of
the sleepers.
The spacing between the rails is referred to as
the gauge, always measured between the
inner faces of the rails. The original soil below the ballast (or a
strengthened substitute) is
called the formation.
Components and Functions
The track structure is made up of subgrade, sub-ballast, ballast,
ties and rail as illustrated
in Figure . Each of these contributes to the primary function of the
track structure, which
is to conduct the applied loads from train traffic across the
subgrade safely. The
magnitudes of typical stresses under a 50,000 lb axle load are shown
in Figure 4-5. These
stresses are applied repeatedly, and each repetition causes a small
amount of deformation
in the subgrade. In theory, the track structure should be designed
and constructed to limit
rail deflections to values which do not produce excessive rail wear
or rates of rail failure.
In reality, cumulative deformation of the subgrade causes distortion
of the subgrade,
leading to formation of .ballast pockets"(Figure 4-6) or outright
shear failure.
Subgrade
The purpose of the subgrade is to support the track structure with
limiting deflections.
Every subgrade will undergo some deflection (strain) as loads
(stress) are applied. The
total displacement experienced by the subgrade will be transmitted
to other components
in the track structure. The stiffer the subgrade (i.e., the higher
the modulus of elasticity),
the lower the deflection values will be. It is important that
adequate subgrade strength
and stiffness be available on a year-round basis, particularly
during spring thaw and
following heavy precipitation events.
The strength, stiffness and total deflection of the subgrade can be
improved by:
Carefully selecting materials that are naturally strong (sand,
gravel, boulders) with
a high angle of internal friction.
Limiting access to water to avoid buildup of pore water pressure and
subsequent
reduction of strength.
Improving the soil properties, using techniques such as compaction,
in situ
densification, grouting and preloading.
Maintain good drainage.
Maintain stable subgrade geometry.
Sub-ballast
The purpose of sub-ballast is to form a transition zone between the
ballast and subgrade
to avoid migration of soil into the ballast, and to reduce the
stresses applied to the
subgrade. In theory, the gradation of the sub-ballast should form a
filter zone that
prevents migration of fine particles from the subgrade into the
ballast. In practice,
insufficient attention has been placed to sub-ballast gradation
historically, and much of
the sub-ballast does not adequately perform that function. This
notwithstanding, the
number of occurrences of subgrade contamination of ballast is
relatively few.
Switch Ties
Switch ties are commonly hardwood species, usually provided in
either
6" or 12" increments beginning at 9'-0" up to
23'-0" in length. Nominal cross-section
dimensions are 7" x 9", although larger ties are specified by some
railways. The primary
use for switch ties is relegated to turnouts (thus their name).
However, they are also used
in bridge approaches, crossovers, at hot box detectors and as
transition ties. Some
railways use switch ties in heavily traveled road crossings and at
insulated rail joints.
Switch ties ranging in length from 9'-0" to 12'-0" can also be used
as "swamp" ties.
The extra length provides additional support for the track in swampy
or poor-drained
areas. Some railways have utilized Azobe switch ties (an extremely
dense African wood)
for high-speed turnouts. The benefits associated with reduced plate
cutting and fastener
retention may be offset by the high import costs of this timber.
Softwood Ties
Softwood timber is more rot resistant than hardwoods, but does not
offer the resistance of
a hardwood tie to tie plate cutting, gauge spreading and spike hole
enlargement (spike
killing).Softwood ties also are not as effective in transmitting the
loads to the ballast
section as the hardwood tie. Softwood and hardwood ties must not be
mixed on the main
track except when changing from one category to another. Softwood
ties are typically
used in open deck bridges.
Concrete ties are rapidly gaining acceptance for heavy haul mainline
use, (both track and
turnouts), as well as for curvature greater than 2�. They can be
supplied as crossties (i.e.
track ties) or as switch ties. They are made of pre-stressed
concrete containing reinforcing
steel wires. The concrete crosstie weighs about 600 lbs. vs. the 200
lb. timber track tie.
The concrete tie utilizes a specialized pad between the base of the
rail and the plate to
cushion and absorb the load, as well as to better fasten the rail to
the tie. Failure to use
this pad will cause the impact load to be transmitted directly to
the ballast section, which
may cause rail and track surface defects to develop quickly. An
insulator is installed
between the edge of the rail base and the shoulder of the plate to
isolate the tie
(electrically). An insulator clip is also placed between the contact
point of the elastic
fastener used to secure the rail to the tie and the contact point on
the base of the rail.
Steel Ties
Steel ties) are often relegated to specialized plant locations or
areas not favorable to the
use of either timber or concrete, such as tunnels with limited
headway clearance. They
have also been utilized in heavy curvature prone to gage widening.
However, they have
not gained wide acceptance due to problems associated with shunting
of signal current
flow to ground. Some lighter models have also experienced problems
with fatigue
cracking.
Rail Joints:
The purposes of the rail joint (made up of two joint bars or more
commonly called angle
bars) are to hold the two ends of the rail in place and act as a
bridge or girder between the
rail ends.6 The joint bars prevent lateral or vertical movement of
the rail ends and permit
the longitudinal movement of the rails for expanding or contracting.
The joint is
considered to be the weakest part of the track structure and should
be eliminated
wherever possible. Joint bars are matched to the appropriate rail
section. Each rail section
has a designated drilling pattern (spacing of holes from the end of
the rail as well as
dimension above the base) that must be matched by the joint bars.
Although many
sections utilize the same hole spacing and are even close with
regard to web height, it is
essential that the right bars are used so that fishing angles and
radii are matched. Failure
to do so will result in an inadequately supported joint and will
promote rail defects such
as head and web separations and bolt hole breaks. There are three
basic types of rail
joints
Standard
Compromise
Insulated
Standard Joints
Standard joint bars connect two rails of the same weight and
section. They are typically
24" in length with 4-bolt holes for the smaller rail sections or 36"
in length with 6-bolt
holes for the larger rail sections. Alternate holes are elliptical
in punching to
accommodate the oval necked track bolt. Temporary joints in CWR
require the use of the
36. bars in order to permit drilling of only the two outside holes
and to comply with the
FRA Track Safety Standard's requirement of maintaining a minimum of
two bolts in each
end of any joint in CWR.
Compromise Joints
Compromise bars connect two rails of different weights or sections
together. They are
constructed such that the bars align the running surface and gage
sides of different rails
sections. There are two kinds of compromise joints:
Directional (Right or Left hand) compromise bars are used where a
difference in
the width of the head between two sections requires the offsetting
of the rail to
align the gage side of the rail.
Non-directional (Gage or Field Side) are used where the difference
between
sections is only in the heights of the head or where the difference
in width of rail
head is not more than 1/8" at the gage point. Gauge point is the
spot on the gauge
side of the rail exactly 5/8" below the top of the rail.
To determine a left or right hand compromise joint:
Stand between the rails at the taller rail section.
Face the lower rail section
The joint on your right is a "right hand".
The joint on your left is a "left hand".
GENERAL ANALYSIS
Alignment of Tracks
The route upon which a train travels and the track is constructed is
defined as an
alignment. An alignment is defined in two fashions. First, the
horizontal alignment
defines physically where the route or track goes (mathematically the
XY plane). The
second component is a vertical alignment, which defines the
elevation, rise and fall (the Z
component).Alignment considerations weigh more heavily on railway
design versus
highway design for several reasons. First, unlike most other
transportation modes, the
operator of a train has no control over horizontal movements (i.e.
steering). The guidance
mechanism for railway vehicles is defined almost exclusively by
track location and thus
the track alignment. The operator only has direct control over
longitudinal aspects of train
movement over an alignment defined by the track, such as speed and
forward/reverse
direction. Secondly, the relative power available for locomotion
relative to the mass to be
moved is significantly less than for other forms of transportation,
such as air or highway
vehicles. Finally, the physical dimension of the vehicular unit (the
train) is extremely
long and thin, sometimes approaching two miles in length. This
compares, for example,
with a barge tow, which may encompass 2-3 full trains, but may only
be 1200 feet in
length. These factors result in much more limited constraints to the
designer when
considering alignments of small terminal and yard facilities as well
as new routes
between distant locations.
The designer MUST take into account the type of train traffic
(freight, passenger, light
rail, length, etc.), volume of traffic (number of vehicles per day,
week, year, life cycle)
and speed when establishing alignments. The design criteria for a
new coal route across
the prairie handling 15,000 ton coal trains a mile and a half long
ten times per day will be
significantly different than the extension of a light rail (trolley)
line in downtown San
Francisco curves as D (degrees per 20 meter arc). However, there
does not seem to be
any widespread incorporation of this practice. When working with
light rail or in metric
units, current practice employs curves defined by radius.
As a vehicle traverses a curve, the vehicle transmits a centrifugal
force to the rail at the
point of wheel contact. This force is a function of the severity of
the curve, speed of the
vehicle and the mass (weight) of the vehicle. This force acts at the
center of gravity of the
rail vehicle. This force is resisted by the track. If the vehicle is
traveling fast enough, it
may derail due to rail rollover, the car rolling over or simply
derailing from the combined
transverse force exceeding the limit allowed by rail-flange contact.
This centrifugal force can be counteracted by the application of
super elevation (or
banking), which effectively raises the outside rail in the curve by
rotating the track
structure about the inside rail. (See Figure) The point, at which
this elevation of the outer
rail relative to the inner rail is such that the weight is again
equally distributed on both
rails, is considered the equilibrium elevation.
Track is rarely super elevated to the
equilibrium elevation. The difference between the equilibrium
elevation and the actual
superelevation is termed under balance. Though trains rarely
overturn strictly from
centrifugal force from speed (they usually derail first). This same
logic can be used to
derive the overturning speed. Conventional wisdom dictates that the
rail vehicle is
generally considered stable if the resultant of forces falls within
the middle third of the
track. This equates to the middle 20 inches for standard gauge track
assuming that the
wheel load upon the rail head is approximately 60-inches apart.
As this resultant force begins to fall outside the two rails, the
vehicle will begin to tip and
eventually overturn. It should be noted that this overturning speed
would vary depending
upon where the center of gravity of the vehicle is assumed to be.
There are several factors, which are considered in establishing the
elevation for a curve.
The limit established by many railways is between five and
six-inches for freight
operation and most passenger tracks. There is also a limit imposed
by the Federal
Railroad Administration (FRA) in the amount of under balance
employed, which is
generally three inches for freight equipment and most passenger
equipment.
Underbalance limits above three to four inches (to as much as five
or six inches upon
FRA approval of a waiver request) for specific passenger equipment
may be granted after
testing is conducted. Track is rarely elevated to equilibrium
elevation because not all
trains will be moving at equilibrium speed through the curve.
Furthermore, to reduce both the maximum allowable super elevation
along with a
reduction of under balance provides a margin for maintenance. Super
elevation should be
applied in 1/4-inch increments in most situations. In some
situations, increments may be
reduced to 1/8 inch if it can be determined that construction and
maintenance equipment
can establish and maintain such a tolerance. Even if it is
determined that no
superelevation is required for a curve, it is generally accepted
practice to superelevate all
curves a minimum amount (1/2 to 3/4 of an inch).
Each railway will have its own
standards for superelevation and under balance, which should be used
unless directed
The transition from level track on tangents to curves can be
accomplished in two ways.
For low speed tracks with minimum superelevation, which is commonly
found in yards
and industry tracks, the superelevation is run-out before and after
the curve, or through
the beginning of the curve if space prevents the latter. A commonly
used value for this
run-out is 31-feet per half inch of superelevation.
On main tracks, it is preferred to establish the transition from
tangent level track and
curved super elevated track by the use of a spiral or easement
curve. A spiral is a curve
whose degree of curve varies exponentially from infinity (tangent)
to the degree of the
body curve. The spiral completes two functions, including the
gradual introduction of
superelevation as well as guiding the railway vehicle from tangent
track to curved track.
The curve and the first portion of tangent past the curve due to the
sudden introduction
and removal of centrifugal forces associated with the body curve.
There are several different types of mathematical spirals available
for use, including the
clothoid, the cubic parabola and the lemniscate. Of more common use
on railways are the
Searles, the Talbot and the AREMA 10-Chord spirals, which are
empirical
approximations of true spirals. Though all have been applied to
railway applications to
Alignment Design
All railway alignments would be tangent and flat, thus providing for
the most economical
operations and the least amount of maintenance. Though this is never
the set of
circumstances from which the designer will work, it is that ideal
that he/she must be
cognizant to optimize any design.
From the macro perspective, there has been for over 150 years, the
classic railway
location problem where a route between two points must be
constructed. One option is to
construct a shorter route with steep grades. The second option is to
build a longer route
with greater curvature along gentle sloping topography. The
challenge is for the designer
to choose the better route based upon overall construction,
operational and maintenance
criteria. Such an example is shown below.
Suffice it to say that in today's environment, the designer must
also add to the decision
model environmental concerns, politics, land use issues, economics,
long-term traffic
levels and other economic criteria far beyond what has traditionally
been considered.
These added considerations are well beyond what is normally the
designer's task of
alignment design, but they all affect it. The designer will have to
work with these issues
occasionally, dependent upon the size and scope of the project.
On a more discrete level, the designer must take the basic
components of alignments,
tangents, grades, horizontal and vertical curves, spirals and
superelevation and construct
an alignment, which is cost effective to construct, easy to
maintain, efficient and safe to
operate. There have been a number of guidelines, which have been
developed over the
past 175 years, which take the foregoing into account. The
application of these guidelines
will suffice for approximately 75% of most design situations. For
the remaining
situations, the designer must take into account how the track is
going to be used (train
type, speed, frequency, length, etc.) and drawing upon experience
and judgment, must
make an educated decision. The decision must be in concurrence with
that of the eventual
owner or operator of the track as to how to
produce the alignment with the release of at
least one of the restraining guidelines.
Though AREMA has some general guidance for alignment design, each
railway usually
has its own design guidelines, which complement and expand the AREMA
recommendations. Sometimes, a less restrictive guideline from
another entity can be
employed to solve the design problem. Other times, a specific
project constraint can be
changed to allow for the exception. Other times, it.s more
complicated, and the designer
must understand how a train is going to perform to be able to make
an educated decision.
The following are brief discussions of some of the concepts which
must be considered
when evaluating how the most common guidelines were established.
A freight train is most commonly comprised of power and cars. The
power may be one or
several locomotives located at the front of a train. The cars are
then located in a line
behind the power. Occasionally, additional power is placed at the
rear, or even in the
center of the train and may be operated remotely from the head-end.
The train can be
effectively visualized for this discussion as a chain lying on a
table. We will assume for
the sake of simplicity that the power is all at one end of the
chain.
Trains, and in this example the chain, will always have longitudinal
forces acting along
their length as the train speeds up or down, as well as reacting to
changes in grade and
curvature. It is not unusual for a train to be in compression over
part of its length negative
longitudinal force) and in tension (positive) on another portion.
These forces are often
termed .buff. (Negative) and draft (Positive) forces. Trains are
most often connected
together with couplers (Figure 6-10). The mechanical connections of
most couplers in
North America have several inches (up to six or eight in some cases)
of play between
pulling and pushing. This is termed slack.
If one considers that a long train of 100 cars may be 6000' long,
and that each car might
account for six inches of slack, it becomes mathematically possible
for a locomotive and
the front end of a train to move fifty feet before the rear end
moves at all. As a result, the
dynamic portion of the buff and draft forces can become quite large
if the operation of the
train, or more importantly to the designer, the geometry of the
alignment contribute
significantly to the longitudinal forces.
As the train moves or accelerates, the chain is pulled from one end.
The force at any point
in the chain is simply the force being applied to the front end of
the chain minus the
frictional resistance of the chain sliding on the table from the
head end to the point under
consideration.
As the chain is pulled in a straight line, the remainder of the
chain follows an identical
path. However, as the chain is pulled around a corner, the middle
portion of the chain
wants to deviate from the initial path of the front-end. On a train,
there are three things
preventing this from occurring. First, the centrifugal force, as the
rail car moves about the
curve, tends to push the car away from the inside of the curve. When
this fails, the wheel
treads are both canted inward to encourage the vehicle to maintain
the course of the track.
The last resort is the action of the wheel flange striking the rail
and guiding the wheel
back on course.
Attempting to push the chain causes a different situation. A gentle
nudge on a short chain
will generally allow for some movement along a line. However, as
more force is applied
and the chain becomes longer, the chain wants to buckle in much the
same way an
overloaded, un-braced column would buckle. The
same theories that Euler applied to
column buckling theory can be conceptually applied to a train under
heavy buff forces.
Again, the only resistance to the buckling force becomes the
wheel/rail interface.
Drainage is the subject of storm water behavior as it relates to the
properties of hydrology
and hydraulics. This is a subject that is constantly being reviewed
on a regular basis
within the regulatory bodies of government and it is therefore
always important to review
local requirements to guide the engineer through the design process.
Even though one
method of analysis may be appropriate to use in an area one feels
comfortable in, it may
not be appropriate in another location. A good rule of thumb is to
contact the local
highway department as a starting point and continue your
investigation to local
authorities.
The engineer needs to be aware that one has to maintain existing
drainage patterns and
not increase headwaters upstream or downstream. Adjacent property
owners, whether
they are farmers or city dwellers, have certain rights and are
protected under common
law concerning storm water conveyance and elevation as it relates to
property damage.
GENERAL RECCOMMENDATION
Signal System
Railway signaling techniques shall be applied at various LRT
locations to enhance safety
in the movement of trains and to improve the overall efficiency of
train operations. These
functions include the protection and control of track switches; the
protection and control
of bi-directional train operation where applicable; the protection
for following trains
operating with the normal current of traffic; and highway grade
crossing warning. The
need for signaling, and the type of signalization provided, shall be
determined by the
specific requirements of each line segment.
Automatic Block System
Automatic Block System (ABS) shall be installed at certain locations
along the LRT
right-of-way to permit higher operating speeds than would be
possible by relying on line-
of-sight operation without signals. The ABS system shall provide
information to train
operators concerning the condition and occupancy of the track ahead,
and provide
sufficient stopping distance, when required. Automatic Train Stop
(ATS) shall be
provided if a train passes a stop signal. A violation of a stop
signal shall be reported to
the Operations Control Center by means of the SCADA system.
Unless limited by operational constraints, all signals shall comply
with a "double red"
philosophy. Cab signals functioning in a "go-no-go" environment
shall provide
enforcement for all signaled moves, including those against the
normal direction of
traffic. There shall be no overlap where the next signal in advance
is an "END ABS"
sign.
All signals shall be controlled, in regard to any track switch in
the block, to display a red
aspect when:
The switch points are not in position for safe train movement.
A hand operated switch is not in the normal position.
A switch-and-lock movement is not fully locked.
An electric switch-locking movement is not fully normal.
The selector lever of a dual-control switch-and-lock movement is not
in the
"MOTOR" position.
A manual switch electric lock access door is not fully closed.
No signal shall display an aspect less restrictive than approach,
when the next signal, in
advance, displays an aspect requiring a stop. Three-aspect,
non-interlocked signals shall
display a proceed aspect when the next signal, in advance, displays
an approach aspect.
Interlockings
Interlocking shall be provided for all power switches used on the
mainline in open track.
Interlocking signals shall be provided to govern train movements
into and through
interlocking limits. Detector, time, route, and approach locking
shall be provided at all
interlocking. Detector locking shall not be released until five
seconds after the slow pick-
up track repeater relays have closed their front contacts.
All non-interfering train movements, through interlocking, shall be
permitted
simultaneously.
Interlocking design shall comply with principles and accepted
practices of the
Association of American Railroads (AAR).
Highway Grade Crossing Warning
Warning devices for highway grade crossings shall be installed at
certain locations. Each
such crossing shall include automatic gates, LED flashing lights,
bells, signs, approach
and island track circuits, emergency batteries and associated
circuitry, cabling and cases
as required. Crossing gates shall be Western-Cullen-Hayes model
number 3593-131 with
"Gate Keeper" protective devices or approved equal.
The design of each crossing shall be specific to that site and shall
provide a minimum of
20 seconds warning time, from the time that the lights first begin
to flash until the time
that a train traveling at track speed enters the crossing. The
design of the crossing
circuitry shall avoid unnecessary delays to motorists. Where
necessary, the grade
crossing warning system shall preempt adjacent traffic lights to
avoid automobiles
forming a queue across the tracks.
Center lane Divider Island shall be installed at all grade crossings
to aid in the prevention
of traffic gate runarounds. Crossings with permitted train speeds in
excess of 30 mph
shall have warning signs "High Speed Trains" with flashing yellow
lights facing highway
traffic. Provisions for the installation of video monitoring
equipment shall be installed at
each grade crossing. Highway grade crossing warning devices will be
installed consistent
with AAR Signal Manual and the Manual on Uniform Traffic Control
Devices Standards
(MUTCD).
Train to-Wayside-Communication System (TWC)
RTD's LRVs are equipped with a Train-to-Wayside Communication (TWC)
system. The
carborne portion of the TWC system consists of two transponders (one
for each end of
the LRV), and two car control units (one for each cab). The wayside
portion shall consist
of an inductive loop antenna and a wayside transceiver. The wayside
transceiver, through
the wayside loop antenna, shall constantly transmit a message asking
that any carborne
TWC transponder, in the immediate area, identify itself. A carborne
TWC transponder
receiving this message shall respond by transmitting a serial 19-bit
message, identifying
the LRV's car number, the train number, route number (destination),
and other
information. Thumb-wheel switches and push buttons in each cab are
provided to train
operators to enter the route number and train number of their
consist and other requests
such as switch call and preempt call.
A TWC system, compatible with the LRV equipped TWC system, shall be
installed at all
interlocking, at all passenger stations adjacent to highway
crossings and provisions made
for all passenger stations in street running, and at all power
switches in street running, to
allow train operators to enter switch call and route requests. Use
of the TWC system shall
be the primary method of entering route, switch requests, and SCADA
train identification
at those locations.
A TWC loop and hand hole shall be installed at all highblock for
improved SCADA
control of LRV movements. It shall include a TWC antenna and
conduits to a nearby
signal case for future utilization.
The TWC wayside interrogator operating
frequency shall be 100 Khz. It must be capable
of recording and storing data history to include all inputs and
outputs for download and
review for a backlog of at least 48 hours from the time of download.
Data acquisition and
unit programming must be easily accomplished by a signal technician
with moderate
laptop computer skills. Installation shall include one interrogator
per loop. The wayside
loop shall be a single wire loop mounted between the rails with the
end to end dimension
of the loop being 15 feet. The loop shall be mounted no higher than
top of rail and no
lower than 6 inches below top of rail. In open track areas the loop
shall be housed in a
pre-fabricated protective non-metallic enclosure.
Assignment of destination codes shall take into consideration future
expansion plans of
the LRT system. Assignments shall be developed to provide a logical
progression of
destination codes throughout RTD's LRT expansion plans.
Standard and Codes
The signal system shall be designed, constructed and tested in
accordance with to the
latest revision at the time of award of contract of the following
codes and standards:
U.S. Code of Federal Regulations (CFR), Title 49, Part 236
American Railway Engineering and Maintenance Association (AREMA)
o Signal Manual of Recommended Practice
o American Railway Signaling Principles and Practice
o Communication Manual of Recommended Practice
o Typical Circuits Representing Current Practice for Railway
Signaling
Rules and Regulations of the Colorado Public Utilities Commission
(PUC)
National Electrical Code (NEC)
National Electrical Safety Code (NESC)
Insulated Cable Engineers Association (ICEA)
American Society for Testing and Materials (ASTM)
American National Standards Institute, Inc. (ANSI)
Underwriters Laboratories, Inc. (UL)
U.S. Department of Transportation, Federal Highway Administration,
Manual on
Uniform Traffic Control Devices (MUTCD)
Institute of Electrical and Electronic Engineers (IEEE)
Safety design
Train safety shall be the prime consideration in the design of the
signal system and in the
selection of its components, including relays and other devices with
moving parts,
insulated wire, wire terminals, binding posts, housings, conduits,
resistors, capacitors,
transformers, inductors and other similar items. The entire signal
system shall meet the
requirements of this section. Circuit design
shall conform to the "American Railway
Signaling Principles and Practices" of the AAR Communication and
Signal Section.
The following requirements shall govern the design of the portions
of the system or a
subsystem which affect train safety:
Only components which have high reliability and predictable failure
modes and
rates and which have been proven in conditions similar to the
projected service
shall be utilized.
Components shall be combined in a manner that ensures that a
restrictive rather
than a permissive condition will result from component failure.
All circuits which are not confined to one housing and which affect
safety shall
be double-wire, double-break, except signal and switch indicator
light circuits.
The design shall be based on closed circuit principles.
Component or system failures shall cause a more restrictive signal
indication than
that permitted with no failure. The built-in fault detection and
alarm generation
capability are preferred.
System safety design shall be such that any single independent
component or
subsystem failure will result in a safe condition. Failures that are
not independent
(those failures which in turn always cause others) shall be
considered in
combination as a single failure and will not cause an unsafe
condition.
Any latent failure of the equipment, that is a failure, which by
itself does not
result in an unsafe condition, but which in combination with second
or subsequent
failures could result in an unsafe condition, must be detected and
negated within a
stipulated time period.
Electronic circuit design shall insure that the following types of
component
failures have a restrictive rather than a permissive effect:
o o Two terminal devices: open, short, partial open or short
o o Multi-terminal devices: combination of opens, shorts, partial
opens
and/or partial shorts
Wherever possible, built-in checks shall be included that impose a
restriction
and/or actuate an alarm whenever a device fails to assume its most
restrictive
position when conditions require that it should.
Redundant design by itself shall not be considered an acceptable
method of
achieving design safety.
Headways & Block Layout
The design of the LRT signal system shall provide for minimum train
headways of 130
seconds, or less. Headway is defined as the length of time taken for
a given automatic
block signal to upgrade to a permissive (restricting or approach)
aspect after a leading
train has passed that signal at normal track speed. Maximum train
length will be 4 cars
under normal conditions. Three-aspect signals are required to
provide information about
the aspect displayed by the next signal ahead so as to avoid the
necessity for always
approaching it while prepared to stop.
Wherever it is displayed, a stop indication
shall be an absolute signal, requiring that train
operators bring their trains to a full stop and call the LRT
controller for authorization to
pass the signal at restricted speed (i.e., prepared to stop, within
one-half the range of
vision, short of anything that may so require).
Signal system design headways are calculated without regard for
variations in vehicles,
weather conditions or individual operators. Signal system design
headways will provide
for sustained five minute scheduled headways.
Safe Breaking Distance
Safe braking distances shall be calculated using a 2 second vehicle
reaction time, a
minimum adhesion which would allow a deceleration rate on level
tangent track of 1.95
MPHPS and a 35% (distance) safety margin. The assumed deceleration
rate shall be
reduced on downhill grades to compensate for the effects of gravity.
In addition, all safe
braking distance calculations in open-track territory shall assume a
LRV entry into the
governed area at a maximum authorized speed plus 10 mph to a maximum
of 60 mph.
Train Detection
Train detection in the ABS sections and at interlocking shall be
accomplished by using
one of the following types of track circuits.
Two-rail, shunt type 60 Hz, phase selective track circuits with
impedance bonds
and two-element vital vane relays.
� Solid state electronic, coded track circuits suitable for use in
overhead
propulsion territory.
Single-rail (not to exceed 60 feet in length) or double rail,
shunt-type 60 or 100 Hz AC
track circuits shall be used to detect train presence in embedded
track.
Audio-frequency, overlay, shunt-type track circuits shall be used
for train detection in the
control of highway grade crossing warning equipment.
The design of the LRV propulsion and traction systems and selection
of track circuit
frequencies and modulation schemes shall be coordinated to preclude
interference
between the LRV and the signal system.
A shunt with a resistance of 0.2 ohm or less at any point between
the two rails of any
track circuit shall cause the track circuit to indicate train
occupancy. Shunt fouling shall
not be allowed, and multiple track relays or series fouling shall be
used for all turnouts,
with the exception of the two (or four) turnouts used in crossovers
between mainline
tracks. Voltage regulating transformers in the feed to the track may
be used or additional
track circuits may be installed, if necessary, to provide this
shunting capability.
Impedance bonds shall be used to enhance track circuit stability.
Signals &Switch Indicators
Color Light Signals
With the exception of those signals noted below and two-aspect
interlocking signals,
standard railway color light, high signals, including backgrounds
and split base junction
boxes shall be provided for ABS sections and interlocking in
open-track sections. Signals
at station platforms which do not have to be viewed from a distance
may be dwarf-type
railway color light signals on pedestal bases. Low, dwarf-type
railway color light signals
may be used for non-normal moves.
Signal Aspects
Each signal aspect shall have an indication (meaning), which is the
same wherever it is
displayed throughout the LRT system. The system shall have
two-aspect and three-aspect
signals.
Fundamental aspects of color light signals shall consist of the
following:
Mainline Track Switches
Track Switches in Open-Track
a) Manual Track Switches
Manually operated switches in signaled territory shall be equipped
with switch and lock
movements with operating rods, lock rods and point detectors, and
electric switch locks
as required by Federal Railroad Administration (FRA) requirements.
Removing a
padlock from the electric switch lock and opening the front access
door shall put
neighboring signals to stop and shall start a timer to ensure
clearance of trains that may
have just passed the controlling signals. Expiration of the 30
second timer shall permit
the switches to be unlocked and hand lined.
b) Powered Track Switches
Ballasted
Switches shall be powered by dual control (motor driven/manual)
switch machines on
open trackwork. Power for the dual control switch machines shall be
from the signal
power line or from commercial 120 VAC power source, rectified to 110
VDC. Switch
machines shall be equipped with operating rods, lock rods and point
detectors. Electric
switch and lock movements shall be US & S Type M23-A, GRS model 5F,
or approved
equal.
c) Switch Heaters/Snow Melters
Switch heaters are to be provided and installed by the Signal
Contractor at designated
locations where the presence of ice and snow could affect rail
service. Switch heaters
shall be operated automatically or manually and an indicator shall
be provided at the
control equipment enclosure to indicate that the unit is on. Snow
melters shall be
powered from a 208 or 240 VAC source with heater pads wired in
parallel sufficiently
rated to keep the switch points and stock rails free of snow and
ice.
Track Switches in Paved Track
a) Manual Track Switches
Manual track switches shall be equipped with toggle type switch
movements. Facing-
point switches shall be equipped with switch circuit controllers and
switch indicator as
determined by RTD
b) Powered Track Switches
Embedded
For in street running switches designed for embedded in street
applications shall be
utilized. Switches shall be powered off a rectified AC source
originating from the control
enclosure. Power shall be a nominal 120 VAC. Switch machines shall
be equipped with
operating rods and point detectors. Switches shall be Western Cullen
Hayes, electro-
hydraulic, or approved equal.
A successful operating record shall require a minimum of 3 years of
successful operation
on a comparable North American transit system or railroad, as
determined and approved
by RTD.
ACUTALIZATION
VITAL MICROPROCESSOR INTERLOCKING SYSTEMS
If interlocking is not controlled by vital relays, then Vital
Microprocessor Interlocking
Systems (VMIS) shall be employed to execute all vital safety signal
system functions.
The VMIS system shall be compatible with the existing microprocessor
equipment
currently in service on the RTD light rail system.
The VMIS shall be capable of operating in a light rail transit
environment including
exposure to temperatures, humidify and vibration. The VMIS shall be
capable of
operation at temperature of -40�C to +70�C at 90% humidity
non-condensing.
The VMIS software systems shall be segregated into two independent
software levels as
follows:
Executive Software shall consist of the coding that performs the
input, internal
and output operations that is defined within the individual
interlocking application
logic. The executive software shall be configured on a closed loop
principle to
ensure that the individual vital microprocessors operate in a
fail-safe manner. The
executive software shall reside in a read only memory.
Application Software shall be segregated from the executive software
and consists
of the vital signal logic defining a specific interlocking
configuration. The
application software shall derive its safety from signal circuit
design practices
similar to that used for relay logic. The application software shall
be capable of
being modified to reflect changes in a specific interlocking
configuration by RTD
signal engineering staff with basic computer skills. To perform
these software
modifications, the VMIS system shall incorporate an application
software
development system and software simulator in order that the
modifications can be
tested and verified prior to final implementation.
For large interlocking (more than four power switches and/or movable
point frogs), the
VMIS system shall be segregated into zones and configured in a
manner that failure in
one zone will not affect the operation of an adjacent zone.
Redundant microprocessors
(normal and hot standby) shall be provided at selected
microprocessor interlocking
locations and configured such that shut down of the primary
microprocessor would
automatically permit seamless transfer to the standby unit.
Individual VMIS units shall include both vital serial ports to
interface with adjacent
VMIS unit, and non-vital serial ports for interface with the
non-vital control system.
Interface connections to wayside signal equipment shall be designed
to function with
existing RTD signal equipment operating at standard voltages for the
type of equipment
in service. Where necessary, the VMIS system shall include vital
relays to provide
interface to wayside signal appliances.
The VMIS shall be equipped with a data recorder
and diagnostic system capable of being
accessed on-site at the VMIS location, or remotely over telephone or
dedicated data lines
using a diagnostic terminal or standard laptop personal computer.
Data shall be capable
of being accessed remotely from the data recorder and in real time
on-site directly from
the VMIS equipment. The diagnostic system shall be capable of
identifying a failure, the
nature of the failure and failure location. In addition to the
diagnostic system, individual
cards including; input/output boards, central processor cards and
internal power supply
boards shall be equipped with indicator lights that illuminate when
respective
input/output devices or ports are active.
The VMIS system shall be configured to operate from local available
signal system
power supply sources. Individual VMIS units shall be equipped with
protection against
unwarranted power surges at the power supply input terminals. The
VMIS units shall also
be protected against high levels of electric noise transmitted from
external sources
including radio, vehicle propulsion systems and hi-tension
commercial power lines.
Lightening protection including appropriate lightening arresters and
equalizers shall be
provided at all input terminals interfacing with wayside signal
appliances.
VMIS units shall be modular and consist of stand alone card files
capable of being
mounted in standard instrument racks. Included in the instrument
rack shall be all signal
equipment required to provide a complete stand alone system.
PROGRAMMABLE LOGIC CONTROL SYSTEM
A Programmable Logic Control (PLC) system shall be employed for
control and
indication of the signal system. The PLC system shall interface with
the VMIS at
individual field locations. The PLC system shall perform all
entrance-exit functions,
receive inputs from various sub-system components (including;
individual local control
panels and central control) and transmit the appropriate command to
the VMIS system.
Status indications received from the VMIS shall be processed and
transmitted to the local
control panel and central control. The PLC system shall be
compatible with equipment
currently in-service on RTD's LRT system.
The PLC system shall consist of a fault tolerant microprocessor
based control system,
utilizing either a single unit or fully redundant normal and standby
microprocessors. The
RTD shall determine which locations require redundant systems based
upon the affects a
failure of the microprocessor would have on overall system
operations. The normal and
standby units shall exchange information on operations and health of
each respective unit
over a serial link. Automatic switch over to the standby unit shall
occur if a failure is
detected in the hardware or through diagnostic routines of the
on-line unit.
The system software shall be field proven, commercially available
and prevalent in the
industry. The software system shall be designed in a manner that
will permit future
expansion. The application programs shall be stored on Erasable
Programmable Read
Only Memory (EPROM), with temporary data (controls and indications)
stored in
Random Access Memory (RAM). The software shall
be capable of being modified to
reflect changes in system configuration by RTD signal engineering
staff with basic
computer skills. To perform these software modifications, the
non-vital PLC system shall
incorporate a software development system and software simulator in
order that the
modifications can be tested and verified prior to final
implementation.
The PLC units shall be capable of operation in a light rail transit
environment including
exposure to temperatures, humidify and vibration. The PLC shall be
capable of operation
at temperatures of -40�C to +70�C at 90% humidity non-condensing.
The PLC unit shall
be protected against high levels of electrical noise transmitted
from external sources
including radio, vehicle propulsion systems and hi-tension
commercial power lines. In
addition, appropriate lightening protection shall be provided where
the PLC unit
interfaces with external cable systems.
The PLC units shall consist of modular card files capable of being
mounted in standard
instrument racks. Individual cards including; input/output boards,
central processor
boards and internal power supply boards shall be equipped with
indicator lights that
illuminate when functions on the boards are active.
CONCLUSION
Railroads have had a profound impact on civilization. Most
importantly, the efficiency
and speed of rail travel allow a nation's population, industry, and
agriculture to be
established throughout that nation's territory, even in previously
remote areas. Rail
transportation has also played a significant role in urban
transportation systems. In many
countries, rail continues to be the main mode of passenger travel.
In Europe and Japan,
major cities are connected by high-speed passenger trains, such as
the French TGV (Train
� Grande Vitesse) and the Japanese Shinkansen trains, popularly
known as bullet trains.
References:
C. F. Allen, Railway Curves and Earthwork, 6th ed. (New York:
McGraw-Hill, 1920).
American Railway Engineering and Maintenance of Way Association
(AREMA).
Manual for Railway Engineering. Washington, D.C., 1998.
|
|
|
dd |
|
|
|
|
|
|
|
|
|
|